Submit a Project Change Request

Summary

[OTS-PPMO]

Body

A formal change request (CR) is required when any change is needed to a project's, scope, time line, hours or budget. This includes:

  • Any change to project scope
  • Any change to project start or end dates
  • An individual resource’s hours will exceed the estimated (role forecast) hours by more than 20%
  • The total project hours will exceed the total estimated (role forecast) hours by more than 20%
  • Any new resource needs to be added to a project (regardless of # of hours)
  • Any increase to project budget/expenses

All CRs require OTS leadership approval before any change is to be implemented, so it is critical that a CR is submitted prior to any changes are made or before overages occur. 

The project health should reflect a status of yellow in TD until the change is approved. 

Change Requests should be submitted using the Change Request form found on the PPMO Sharepoint site. Be sure to provide a detailed description of the change being requested.

  • Scope: Clearly identify what is being added or removed from scope
  • Schedule: Specify previous and new dates and include new dates for milestone activities
  • Resources: Specify the individual(s) impacted and the changes to schedules and/or hours
  • Budget: Itemize any costs if budget is impacted
  • Impact if the requested change is not approved